What is ERP

SAP Requirement

Procurement cycle

Material master

Vendor Master

PIR-Purchase Info record

Source list

Quota Arrangement

Release Strategy


Release procedure defines, how the document is going to release. The document can be PR, PO, Contract, Scheduled agreement, RFQ. Here we study about the purchase requisition.

Purchase requisition will be created by the respective stake holders of there plant, if a request is created it will go to buyers Que to create purchase order and before that who ever is created purchase requisition he should approve and after that respective manager should approve.

We can create an N number of approvers for the documents like PR, where as an SAP MM consultant its their duty to maintain the release approvers.

We can maintain the release process for respective documents also.

Eg: we can maintain the release strategy for plant or material group also.

To maintain the release procedure for particular document types in SAP MM, we have communication tables/Structure for document types, mentioned below


Document type Communication table


PR- CEBAN

PR, PO, CO, SA, RFQ CEKKO

SES CESSR


In the above-mentioned communication tables are used to know the details for respective document type field component.

We have T-code to help to find the component for the respective field in the communication table, that is SE11, where we can only display the data (ABAP Data), its mainly used to find the component for the document type with the help of communication table.


Eg: CEBAN is used for PR, if we are maintaining the release procedure with respect to plant than we need to find the respective component for the plant filed in PR.

So, go to SE11, maintain the communication table as CEBAN if you are working for PR or else you can maintain CEKKO, CESSR for the remaining data field components.

As mentioned in the example, we have only one condition (Plant) to maintain the release strategy, if I would like to maintain the release strategy with combination of conditions then we need to define as mentioned below.


Note: Important Note: 1 condition = 1 Characteristic

2 Condition = 2 Characteristic


Note: Maintaining the release strategy we need to follow the below steps.


1. Edit Characteristic

2. Edit Class


3. Setup procedure with classification

1. Release Groups

2. Release Codes

3. Release indicator

4. Release strategies

1. Release prerequisites

2. Release statues

3. Classification


Path to go to above release procedure (OLME)


SPRO--

IMG--

Materials Management--

Purchasing--

Purchase requisition--

Release procedure--

With Classification—



Practicing:


Now will maintain the release procedure with respect to purchase group and Item category.

Follow the steps as mentioned above:


Edit Characteristic:

Where 1 condition is equal to 1 characteristic

We have 2 conditions here (purchase group and Item category), so we need to maintain 2 characteristics in the path I mentioned above.

OLME-With Classification


Characteristics: M1(Enter M1 and check whether its maintained already or not by clicking specs icon), if not created already then click on create icon next to the spec.

Here we should maintain the field components (Purchase group and item cat from SE11)

Go to additional data and maintain the table name as: CEBAN

Go to SE11 and take the field components by selecting the Purchase group and item cat.

P.group-EKGRP

Item cat-PSTYP

Now in this characteristic, we need to maintain either P.group filed component or Item cat component, because we mentioned above 1 condition =1 characteristics.

Maintain field name as: PSTYP


Now create an another characteristics for P.group


M2(Enter M2 and check whether its maintained already or not by clicking specs icon), if not created already then click on create icon next to the spec.

Here we should maintain the field components (Purchase group and item cat from SE11)

Go to additional data and maintain the table name as: CEBAN

Go to SE11 and take the field components by selecting the Purchase group and item cat.

P.group-EKGRP

Item cat-PSTYP

Now in this characteristic, we need to maintain either P.group filed component or Item cat component, because we mentioned above 1 condition =1 characteristics.

Maintain field name as: EKGRP


Note: Now we maintained the two characteristics that we want to use for release strategy.


Edit Classes:


Here we should define the class for characteristics, where we maintained 2 characteristics and we cannot maintain all characteristics directly to release strategy.

We need to define a class and we need to link all the characteristics in that class, so that in the next steps we can use class instead of all characteristics.

Go to Edit Class-

Class-M3

Class type-Release strategy

Click on create icon

Maintain the description as “Something relevant like this is for PR to convert to PO”

Go to characteristics-maintain the both Char numbers we created above.

M1

M2

Save


Select “setup procedure with classification


Here we need to do some functions like-release groups, release codes, release indicator, release strategies.


Select-Release group:


We need to maintain a new group in release group and we need to assign the class to this release group

M4 (Newley created group) assigned to M3(Class we defined)

Save


Release Codes


Maintain the release codes.

Group we maintained is M4-code is CR and maintain the description.

Here if we want two approvers then we need to maintain 2 column’s M4 and next to maintain CR-creator and MN-Manager and maintain the description as same.

M4-CR

M4-MN


Release Indicator


Maintain new entries, where we need to maintain the Block and release fields here

B-Block

R-Release


Release Strategy


Maintain release group what we maintained-M3 and release strategy number as 10.

Release codes-Mention

CR

MN

Select Prerequisites—

Select the last tab and continue—


Select release statuses---

Select the last tab as R-so that once we get all approvals PR will allow to create PO.

Select Classification

Item cat-Z

P.group-000

Maintain few values for the fields we defined for release strategy.

Now create the PR with above combination, we will see a new tab in the item level…. Release strategy

Go to ME54N and open the PR and release the PR to create PO.

SAP MM Full Purchasing concepts with configurations

Url: View Details

What you will learn
  • All purchasing related concepts like - Material master/Vendor master/PIR/Source list/Quota//PR/PO/Release strategy

Rating: 4.25

Level: All Levels

Duration: 15 hours

Instructor: Studyuuu SAP MM/EWM


Courses By:   0-9  A  B  C  D  E  F  G  H  I  J  K  L  M  N  O  P  Q  R  S  T  U  V  W  X  Y  Z 

About US

The display of third-party trademarks and trade names on this site does not necessarily indicate any affiliation or endorsement of course-link.com.


© 2021 course-link.com. All rights reserved.
View Sitemap